5-Dec-15 |
System Entry |
Creation of project page.
|
5-Dec-15 |
System Entry |
Project sent for club signatures.
|
5-Dec-15 |
System Entry |
Project signed by Jim Epstein.
|
18-Dec-15 |
System Entry |
Project approved by the District Approval Committee.
|
30-Mar-16 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
1-Jun-16 |
System Entry |
Project has been implemented and final report uploaded.
|
13-Jun-16 |
by Jim Epstein |
Correction: Progress report has been uploaded
|
23-Jun-16 |
by Jim Epstein |
Final report due no later than 6/1/17
|
17-Sep-16 |
by Jim Epstein |
Project reverted to paid status and waiting for final report
|
17-Sep-16 |
by Jim Epstein |
System Entry: Project reverted to 'Paid' status.
|
20-Sep-16 |
by Jim Epstein |
System Entry: Project has been implemented and final report uploaded.
|
20-Sep-16 |
by Jim Epstein |
System Entry: Final report approved by the District Approval Committee.
|