5-May-16 |
System Entry |
Creation of project page.
|
16-Aug-16 |
by David Lesnick |
This project is going forward and we usually distribute the dictionaries in November
|
16-Aug-16 |
by David Lesnick |
System Entry: Project reverted to "Published".
|
16-Aug-16 |
by David Lesnick |
System Entry: Project is now "Fully Pledged".
|
19-Aug-16 |
by Fred Goldman |
System Entry: Project sent for club signatures.
|
19-Aug-16 |
by Fred Goldman |
System Entry: Project signed by Fred Goldman.
|
19-Aug-16 |
by David Lesnick |
System Entry: Project signed by David Lesnick.
|
29-Aug-16 |
by Fred Goldman |
System Entry: Project approved by the District Approval Committee.
|
2-Nov-16 |
by Fred Goldman |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
1-Jun-17 |
by Fred Goldman |
System Entry: Project has been implemented and final report uploaded.
|
1-Jun-17 |
by Fred Goldman |
System Entry: Final report approved by the District Approval Committee.
|