P-1263

Skate Park Security Lighting

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: McCook, NE

Total Budget: $2,000

Area of Focus: Economic and community development

Activity Type: Community Development: General

Summary: Add lighting to Skate Park for the security and safety of the community.


The Skate Park, completed in 2015, has been a great addition to our community of McCook, Nebraska as it is an outlet for the underserved youth of our community. However, the park is set in a dark tree lined area. The need to light the park is a priority for the security, safety and well-being of our community. The total community cost of the project is estimated at $7,200 and consists of 3 lights, 3 poles, and an on-demand timer control for the park area. The possibility of solar lighting is also being discussed which will drive the total project cost upward but alleviate some retroactive cost savings due to the "green" lighting method.

The McCook Rotary Club's Skate Park Security Lighting project will purchase 1 light/pole set, and installation (volunteer man-power) of the lights and equipment. The McCook Rotary Club is requesting $1,000 of District Funds which will be paired with our $1,000 contribution. The remainder of the funds needed for to complete the community project will be provided through other avenues of community financing.

This grant application is our 1st priority grant application. The timeline for completion of the project is set for December 2016.

Project Contact Person

District: 5630

Rotary Club of: McCook

Primary Contact: Sharon Kircher

Email: kirchers@mpcc.edu

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2016-17 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

McCook (5630)

11-May-16

$1,000

$1,000

$2,000

Total

$1,000

$1,000

$2,000

Project Supporting Documents

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

11-May-16

System Entry

Creation of project page.

12-May-16

System Entry

Project is now "Fully Pledged".

12-May-16

System Entry

Project sent for club signatures.

12-May-16

System Entry

Project signed by Sharon Kircher.

19-Jul-16

by Sharon Kircher

Project is on-going.

16-Aug-16

by Scott McLaughlin

System Entry: Project approved by the District Approval Committee.

3-Nov-16

by Randy Kratochvil

System Entry: Check for DDF payment issued by Foundation Treasurer.

14-May-17

by Philippe Lamoise

Status reverted to "Reported" at Scott McLaughlin's request.

14-May-17

by Dale Schultz

System Entry: Project has been implemented and final report uploaded.

14-May-17

by Dale Schultz

System Entry: Final report approved by the District Approval Committee.

14-May-17

by Scott McLaughlin

System Entry: Project reverted to 'Paid' status.

15-May-17

by Sharon Kircher

Final report submitted

15-May-17

by Sharon Kircher

System Entry: Project has been implemented and final report uploaded.

15-May-17

by Dale Schultz

System Entry: Final report approved by the District Approval Committee.