25-May-16 |
by James Epstein |
Sent Welcome message
|
25-May-16 |
System Entry |
Creation of project page.
|
25-May-16 |
System Entry |
Project sent for club signatures.
|
25-May-16 |
System Entry |
Project signed by Rebecca Koppes Conway.
|
25-May-16 |
System Entry |
Project signed by Sean Conway.
|
26-May-16 |
System Entry |
Project signed by Lyn Velle.
|
26-May-16 |
System Entry |
Project signed by Jennifer Owens.
|
4-Jun-16 |
by James Epstein |
Submitted two projects and need to withdraw one of them.
|
6-Jun-16 |
by James Epstein |
Two district grants plus Centennial grant must be $4,000 or less
|
6-Jun-16 |
System Entry |
Signature Process cancelled by user.
|
6-Jun-16 |
System Entry |
Project reverted to "Published".
|
6-Jun-16 |
System Entry |
Project is now "Fully Pledged".
|
6-Jun-16 |
System Entry |
Project sent for club signatures.
|
6-Jun-16 |
System Entry |
Project signed by Jennifer Owens.
|
6-Jun-16 |
System Entry |
Project signed by Rebecca Koppes Conway.
|
6-Jun-16 |
System Entry |
Project signed by Lyn Velle.
|
6-Jun-16 |
System Entry |
Project signed by Ron Hogan.
|
6-Jun-16 |
System Entry |
Project signed by Sean Conway.
|
6-Jun-16 |
System Entry |
Project signed by Joe Schon.
|
15-Jun-16 |
System Entry |
Project approved by the District Approval Committee.
|
28-Jun-16 |
by James Epstein |
Report due no later than June 1, 2017
|
15-Jul-16 |
by Bill Kehl |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
5-Jan-17 |
by Rebecca Koppes Conway |
Redeye Rotary members donated these books for the Migrant Christmas Fiesta. Members also participated on Saturday December 10 to wrap presents and on Saturday December 17 to volunteer. Pictures are available but the site is not uploading at this time. I will do so later but wanted to get the project reported. Rebecca
|
5-Jan-17 |
by James Epstein |
Final report form must be provided along with financial records.
|
5-Jan-17 |
by Rebecca Koppes Conway |
System Entry: Project has been implemented and final report uploaded.
|
5-Jan-17 |
by James Epstein |
System Entry: Project reverted to 'Paid' status.
|
8-Jan-17 |
by Rebecca Koppes Conway |
System Entry: Project has been implemented and final report uploaded.
|
8-Jan-17 |
by James Epstein |
System Entry: Final report approved by the District Approval Committee.
|