2-Jun-16 |
System Entry |
Creation of project page.
|
2-Jul-16 |
by Sharron Miles |
HI Jim, Can you please upload your most recent 990 . We can't approve any grants with out the MOU and 990 being there.
|
23-Aug-16 |
by Richard Sherman |
System Entry: Project sent for club signatures.
|
23-Aug-16 |
by Richard Sherman |
System Entry: Project signed by Richard Sherman.
|
23-Aug-16 |
System Entry |
System Entry: Project signed by Jim Ervin.
|
23-Aug-16 |
System Entry |
System Entry: Project signed by Sharron Miles.
|
25-Aug-16 |
System Entry |
System Entry: Project signed by Christopher Castoro.
|
26-Aug-16 |
by Richard Sherman |
System Entry: Project approved by the District Approval Committee.
|
7-Jul-17 |
by Sharron Miles |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
7-Jul-17 |
by Sharron Miles |
System Entry: Project has been implemented and final report uploaded.
|
7-Jul-17 |
by Sharron Miles |
System Entry: Final report approved by the District Approval Committee.
|