25-Jul-16 |
System Entry |
System Entry: Creation of project page.
|
22-Aug-16 |
by Richard Sherman |
System Entry: Project sent for club signatures.
|
22-Aug-16 |
System Entry |
System Entry: Project signed by Shari Turner.
|
23-Aug-16 |
by Richard Sherman |
System Entry: Project signed by Richard Sherman.
|
28-Aug-16 |
by Karen Severance |
System Entry: Project signed by Karen Severance.
|
12-Oct-16 |
by Karen Severance |
System Entry: Project signed by A.C. Adam.
|
16-Nov-16 |
by Shari Turner |
Our project is going well - dictionaries ordered, principals notified, members picking up dictionaries and setting dates to deliver to 3rd graders at school.
|
16-Nov-16 |
System Entry |
System Entry: Project signed by Sharron Miles.
|
31-Mar-17 |
by Shari Turner |
Dictionaries have been distributed.
|
16-May-17 |
by Sharron Miles |
System Entry: Signature Process cancelled by user.
|
16-May-17 |
by Sharron Miles |
System Entry: Project sent for club signatures.
|
16-May-17 |
by Sharron Miles |
System Entry: Project signed by Sharron Miles.
|
25-May-17 |
by Sharron Miles |
System Entry: Signature Process cancelled by user.
|
25-May-17 |
by Sharron Miles |
System Entry: Project sent for club signatures.
|
26-May-17 |
by Sharron Miles |
System Entry: Project signed by Sharron Miles.
|
29-May-17 |
by Shari Turner |
System Entry: Project signed by Shari Turner.
|
13-Jul-17 |
by Sharron Miles |
System Entry: Project approved by the District Approval Committee.
|
13-Jul-17 |
by Sharron Miles |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
1-Aug-17 |
by Sharron Miles |
System Entry: Project has been implemented and final report uploaded.
|
1-Aug-17 |
by Sharron Miles |
System Entry: Final report approved by the District Approval Committee.
|