P-1546

Esther Shea Field Media Booth

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: Ketchikan, Alaska

Total Budget: $15,000

Area of Focus: Economic and community development

Activity Type: Community Development: General

Summary: Build Media Booth and covered storage at a youth sports field in Ketchikan, Alaska


Ketchikan gets nearly 13 feet of rain every year. Currently patrons, scorekeepers, and media recording or reporting on events at the track and sports field have no weather protection. The field has approximately 400 youth users in organized leagues for soccer, track, and football. It also has many community users. The lack of weather protection also makes it harder to operate the scoreboard when the weather is poor. The project would have the Rotary club acquire materials and design for a two story media booth with storage on the lower floor. The construction would be by club members and community user group volunteers. In connection with this project the local municipality would install ADA accessible bleachers to improve the patron viewing experience. Project costs for the media booth are estimated to total approximately $15,000 total including design. The intention is that the booth would be constructed late summer 2017, weather permitting.

Project Contact Person

District: 5010

Rotary Club of: Ketchikan (The First City)

Primary Contact: Scott Brandt-Erichsen

Email: scottb@kgbak.us

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2017-18 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Ketchikan (The First City) (5010)

9-Feb-17

$12,000

$3,000

$15,000

Total

$12,000

$3,000

$15,000

Project Supporting Documents

Project Photos

History Log Entries

9-Feb-17

System Entry

System Entry: Creation of project page.

15-May-17

by Scott Brandt-Erichsen

Project is under design by R and M engineering.

4-Jun-17

by Denise Ringhand

System Entry: Project sent for club signatures.

5-Jun-17

by Scott Brandt-Erichsen

System Entry: Project signed by Scott Brandt-Erichsen.

18-Jul-17

by Denise Ringhand

System Entry: Project approved by the District Approval Committee.

6-Aug-17

by Charlotte Tharp

System Entry: Check for DDF payment issued by Foundation Treasurer.

17-Feb-18

by Scott Brandt-Erichsen

The Esther Shea Field Media Booth project is now complete. We will be trying to have a dedication ceremony in late March or early April. The only item left is installing the plaque recognizing donations.

4-Mar-18

by Scott Brandt-Erichsen

System Entry: Final Report signed by Scott Brandt-Erichsen.

8-Mar-18

by Denise Ringhand

System Entry: Final report approved by the District Approval Committee.