12-May-17 |
by Don Ehrke |
System Entry: Creation of project page.
|
15-Jun-17 |
by Don Ehrke |
System Entry: Project sent for club signatures.
|
15-Jun-17 |
by Don Ehrke |
System Entry: Project signed by Don Ehrke.
|
6-Sep-17 |
by Don Ehrke |
The project is still a go as planned. I was having problems down loading requesting documents Our club President is working on the process so we can continue on.
|
7-Sep-17 |
by Vickie Klein |
System Entry: Project approved by the District Approval Committee.
|
18-Sep-17 |
by Randy Kratochvil |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
28-Sep-17 |
by Don Ehrke |
We received the $1,000 check this and was deposited into our grant fund account. We are waiting on the camp board to decide where they would like the swing located.
|
2-Apr-18 |
by Don Ehrke |
The project has been delayed only due to the fact the camp joy board had to reconsider what type of playground equipment they could budget and the swing set would be included in the project. Due to a public camp, specific specs are required. The plan is to have the total project completed by the end of April which would include the swing set.
|
8-May-18 |
by Don Ehrke |
On May 6th and 7th the base poles for the swing set were cemented in and final assembly will be done in a couple days which will complete the project.
|
2-Jan-19 |
by Don Peterson |
System Entry: Project has been implemented and final report uploaded.
|
2-Jan-19 |
by Don Peterson |
System Entry: Final report approved by the District Approval Committee.
|