11-May-18 |
by Kathleen Tollaksen |
System Entry: Creation of project page.
|
16-Aug-18 |
by Kathleen Tollaksen |
This project will take place in September, 2018
|
16-Oct-18 |
by Rachel Ossyra |
System Entry: Project sent for club signatures.
|
16-Oct-18 |
System Entry |
System Entry: Project signed by Kathleen Tollaksen.
|
16-Oct-18 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
30-Nov-18 |
by David Phelps |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
11-Jan-19 |
by Kathleen Tollaksen |
System Entry: Project has been implemented and final report uploaded.
|
24-Jan-19 |
by Bill Lyman |
Stewardship review is complete. Meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. WL/LG
|
24-Jan-19 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|