14-May-18 |
by Helen Maxwell |
System Entry: Creation of project page.
|
22-May-18 |
by Helen Maxwell |
System Entry: Project sent for club signatures.
|
22-May-18 |
by Helen Maxwell |
System Entry: Project signed by Helen Maxwell.
|
22-May-18 |
System Entry |
System Entry: Project signed by Bob Kelly.
|
22-May-18 |
System Entry |
System Entry: Project signed by Bob Kelly.
|
22-May-18 |
System Entry |
System Entry: Project signed by Jo Holman.
|
5-Jul-18 |
by Stacey Giannoulis |
System Entry: Project approved by the District Approval Committee.
|
21-Aug-18 |
by Helen Maxwell |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
5-Mar-19 |
by Jo Holman |
Due to the rainy weather and a delay getting seedlings from the nursery (one of the owners past away), we pushed back Arbor Titivation to March 16th and delivery of the seedlings the week of March 18th.
|
16-Mar-19 |
by Helen Maxwell |
The project will take place during the month of March. When completed we will file a final report.
|
30-Apr-19 |
by Jo Holman |
System Entry: Project has been implemented and final report uploaded.
|
16-May-19 |
by Stacey Giannoulis |
System Entry: Final report approved by the District Approval Committee.
|