Project Description

Country: USA

Location: Matanuska-Susitna Borough

Total Budget: $1,250

Areas of Focus: Peace and conflict prevention/resolution, Economic and community development

Activity Type: Community Development: Construction/Renovation

Summary: Install roof snow stops, gas meter cover and video surveillance at community senior center


The Wasilla Senior Center serves a growing population of seniors in the Matanuska-Susitna Borough (MSB) of Alaska, serving primarily those with the most economic need. The population of seniors needing services is rapidly increasing - the MSB has the fastest growing senior population in Alaska. The community center has a continuing problem with snow/ice shedding that endangers seniors entering/exiting. This risk will be alleviated by installing snow stops over the entrance. The building's gas meter is exposed and is at risk of damage from ice/snow accumulation. Also, ice/snow build-up can prevent access to shut off the gas supply in an emergency. Installing a small roof/cover will eliminate the risk. Finally, seniors are experiencing increased crime and have asked to have video surveillance installed to deter crime and provide crime investigation evidence should a crime occur. By installing high-definition exterior surveillance cameras and video storage, the center will be able to record the exterior approaches 24/7/365 and capture images useful to police. The video system used, and camera placement will be selected in collaboration with local law enforcement. This system will be a powerful deterrent, and will provide elders with both peace of mind and a means to address criminal and nuisance activity.

Funds will purchase materials. Rotary volunteers, in collaboration with volunteers from the senior center, will install them.

Project Contact Person

District: 5010

Rotary Club of: Susitna

Primary Contact: Chuck Foster

Email: cfoster176@gmail.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2018-19 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Susitna (5010)

24-May-18

$625

$625

$1,250

Total

$625

$625

$1,250

Project Supporting Documents


[24-Apr-19]
Final Report


[12-May-19]
check 1021


[10-May-19]
check to Jack Timm


[12-May-19]
Chuck receipts


[12-May-19]
SBS receipts


[24-Apr-19]
Snowbreaks


[24-Apr-19]
Sr Safety statement

 

Project Photos

History Log Entries

24-May-18

System Entry

System Entry: Creation of project page.

28-May-18

by Chuck Foster

System Entry: Project sent for club signatures.

28-May-18

by Chuck Foster

System Entry: Project signed by Chuck Foster.

28-May-18

System Entry

System Entry: Project signed by Jack Timm.

28-May-18

by Denise Ringhand

System Entry: Signature Process cancelled by user.

12-Jul-18

by Denise Ringhand

System Entry: Project reverted to "Published".

12-Jul-18

by Denise Ringhand

System Entry: Project is now "Fully Pledged".

12-Jul-18

by Denise Ringhand

System Entry: Project sent for club signatures.

12-Jul-18

by Chuck Foster

System Entry: Project signed by Chuck Foster.

16-Jul-18

by Denise Ringhand

System Entry: Project approved by the District Approval Committee.

30-Jul-18

by Denise Ringhand

Due to the cancellation of another Rotary district grant, $425.00 in additional DDF has been allocated for P-2198. The total amount of DDF will now be $1,050. The club has agreed to match this amount, which brings the total of this grant to $2,100.00

23-Aug-18

by Charlotte G Tharp

System Entry: Check for DDF payment issued by Foundation Treasurer.

17-Mar-19

by Chuck Foster

This project is nearly complete. The housing over the gas main is installed, and most of the snow stops are in. The video surveillance system is operational. We have a few more snow stops to install, but we need the snow to melt from the roofing first.

25-Apr-19

by Jack Timm

This project impacts 200 people per day (6000 annually)

25-Apr-19

by Chuck Foster

System Entry: Final Report signed by Chuck Foster.

29-May-19

by Alex Slivka

System Entry: Final report approved by the District Approval Committee.

© 2010 Philippe Lamoise - Website design by Philippe Lamoise, D2G Online