P-2679

Solar Power for school

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Haiti

Location: Les Cayes

Total Budget: $6,000

Area of Focus: Basic education and literacy

Activity Type: Education: General

Summary: Solar power to provide electricity to schools


Hurricane Matthew destroyed the power grid in the southern district of Haiti in October, 2016. The orphanage/children's community, home to 240 resident children known as Pwoje Espwa (Project Hope), has been without electricity since. The ability of our students to learn without proper lighting and other benefits of power is severely limited. Our schools not only educate our resident students but also local village children who have no public schools to attend. In total, Pwoje Espwa provides education for over 1000 students.

Project Contact Person

District: 5495

Rotary Club of: Four Peaks (Fountain Hills)

Primary Contact: Jack Reynolds

Email: jhrtheoswork@aol.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2019-20 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Four Peaks (Fountain Hills) (5495)

23-Apr-19

$4,000

$2,000

$6,000

Total

$4,000

$2,000

$6,000

Project Supporting Documents

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

23-Apr-19

by Jim Bissonett

Jack, are you trying to raise $41,000 in order to get this project approved? I think you should call me about this. 480-299-4441

23-Apr-19

System Entry

System Entry: Creation of project page.

24-Apr-19

by Jim Bissonett

System Entry: Project is now "Fully Pledged".

24-Apr-19

by Jim Bissonett

System Entry: Project sent for club signatures.

24-Apr-19

System Entry

System Entry: Project signed by Jack Reynolds.

2-Jun-19

by Jim Bissonett

System Entry: Signature Process cancelled by user.

2-Jun-19

by Jim Bissonett

System Entry: Project sent for club signatures.

2-Jun-19

System Entry

System Entry: Project signed by Jack Reynolds.

16-Jun-19

by Jim Bissonett

System Entry: Project approved by the District Approval Committee.

7-Jul-19

by Jim Bissonett

Jack, I can only make the check payable to your club. Where do you want it sent?

6-Aug-19

by Jim Bissonett

System Entry: Check for DDF payment issued by Foundation Treasurer.

8-Jan-20

by Jim Bissonett

System Entry: Project has been implemented and final report uploaded.

14-Jan-20

by Jim Bissonett

System Entry: Final report approved by the District Approval Committee.