P-2729

Toilet Block Female students

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Afghanistan

Location: Jalalabad

Total Budget: $8,000

Area of Focus: Water, sanitation and hygiene

Activity Type: Water: Sanitation

Summary: Del Mar


Nangarhar University's Faculty of Education does not have adequate toilet facilities for 322 female students. The Chancellor and Dean have asked if the La Jolla Golden Triangle Rotary Club could provide the same. The Club's representative in Jalalabad, who is also the President of the Jalalabad Rotary Club, has received a proposal to build the toilet facility for $7,805.96. We ask for $8,000 to have a small contingency.Based on our club's past experience in building structures in Jalalabad, we believe this is reasonable.

Attached are construction plans, letter from contactor, letter from Dean, and letter explaining need for facilities.

Project Contact Person

District: 5340

Rotary Club of: La Jolla Golden Triangle

Primary Contact: Steve Brown

Email: stephenrbrown@att.net

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2019-20 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

La Jolla Golden Triangle (5340)

7-May-19

$4,000

$4,000

$8,000

Total

$4,000

$4,000

$8,000

Project Supporting Documents

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

7-May-19

by Steve Brown

System Entry: Creation of project page.

29-Jul-19

by Mike Whitehurst

System Entry: Project sent for club signatures.

29-Jul-19

System Entry

System Entry: Project signed by Stephen Robert Brown.

30-Jul-19

System Entry

System Entry: Project signed by Kim Schafer.

5-Aug-19

by Mike Whitehurst

System Entry: Project approved by the District Approval Committee.

19-Sep-19

by Scott Carr

System Entry: Check for DDF payment issued by Foundation Treasurer.

18-Feb-20

by Steve Brown

System Entry: Final Report signed by Stephen Robert Brown.

18-Feb-20

System Entry

System Entry: Final Report signed by Kim Schafer.

24-Feb-20

by Elana Levens-Craig

Hello,

I just want to let you know that I had to reject the final report because the expenditures weren't listed on the final report. Can you please fill in the $8,000 expenditure and resubmit the final report? Thank you.

Elana

24-Feb-20

by Elana Levens-Craig

System Entry: Project reverted to "Paid".

24-Feb-20

by Steve Brown

System Entry: Final Report signed by Stephen Robert Brown.

24-Feb-20

System Entry

System Entry: Final Report signed by Kim Schafer.

25-Feb-20

by Elana Levens-Craig

System Entry: Project reverted to "Paid".

25-Feb-20

by Steve Brown

System Entry: Final Report signed by Stephen Robert Brown.

25-Feb-20

System Entry

System Entry: Final Report signed by Kim Schafer.

26-Feb-20

by Elana Levens-Craig

System Entry: Final report approved by the District Approval Committee.

© 2010 Philippe Lamoise - Website design by Philippe Lamoise, D2G Online