29-May-19 |
by Paul Donohue |
System Entry: Creation of project page.
|
4-Sep-19 |
by Paul Donohue |
Homewood Rotarian Rodney STrong appointed grant administer for the club. Mr. Strong is preparing eligibility criteria while we await district confirmation funds are available. Expectation is to approve the criteria and award scholarships this fall.
|
4-Sep-19 |
by Paul Donohue |
System Entry: Project sent for club signatures.
|
4-Sep-19 |
by Paul Donohue |
System Entry: Project signed by Paul Donohue.
|
4-Sep-19 |
System Entry |
System Entry: Project signed by Geoff Slawson.
|
12-Sep-19 |
by Susan W Linn |
System Entry: Signature Process cancelled by user.
|
12-Sep-19 |
by Susan W Linn |
System Entry: Project reverted to "Published".
|
12-Sep-19 |
by Susan W Linn |
System Entry: Pledge of $500 DDF by Susan W Linn of the Rotary Club of Orland Park, District 6450.
|
12-Sep-19 |
by Susan W Linn |
System Entry: Project is now "Fully Pledged".
|
13-Sep-19 |
by Paul Donohue |
System Entry: Project sent for club signatures.
|
15-Sep-19 |
by Paul Donohue |
System Entry: Project signed by Paul Donohue.
|
15-Sep-19 |
by Susan W Linn |
System Entry: Signature Process cancelled by user.
|
25-Sep-19 |
by Susan W Linn |
System Entry: Pledge of $500 by Susan W Linn of the Rotary Club of Orland Park, District 6450.
|
25-Sep-19 |
by Susan W Linn |
System Entry: Project sent for club signatures.
|
27-Sep-19 |
by Paul Donohue |
System Entry: Project signed by Paul Donohue.
|
8-Nov-19 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
21-Dec-19 |
by Rachel Ossyra |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
29-Apr-20 |
by Susan W Linn |
This is a reminder that the final report for your grant was due 30 days after completion of your project. Please file your final report now. NOTE: If you haven’t spent all your funds, they can be repurposed for COVID 19. Please contact me for more information about that.
It is ABSOLUTELY CRITICAL that you file your final report NOW. If you don’t, the 2020-21 grant for the ENTIRE District will be DELAYED.
|
6-Jul-20 |
by Susan W Linn |
System Entry: Project has been implemented and final report uploaded.
|
13-Jul-20 |
by lesley Gottlinger |
Stewardship review is complete. Project meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. LG & WL
|
13-Jul-20 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|