19-Jul-19 |
System Entry |
System Entry: Creation of project page.
|
29-Jul-19 |
by Kim Muslusky |
Susan Marsh, Treasurer
|
29-Jul-19 |
by Mike Whitehurst |
System Entry: Project sent for club signatures.
|
29-Jul-19 |
by Kim Muslusky |
System Entry: Project signed by Kim Muslusky.
|
29-Jul-19 |
System Entry |
System Entry: Project signed by Susan Marsh.
|
29-Jul-19 |
by Susan Marsh |
System Entry: Project reverted to "Submitted" - Janice H Kurth added to the list of signatories.
|
29-Jul-19 |
by Susan Marsh |
System Entry: Signature Process cancelled by user.
|
29-Jul-19 |
by Susan Marsh |
System Entry: Project sent for club signatures.
|
29-Jul-19 |
by Susan Marsh |
System Entry: Project signed by Susan Marsh.
|
29-Jul-19 |
by Kim Muslusky |
System Entry: Project signed by Kim Muslusky.
|
5-Aug-19 |
by Mike Whitehurst |
System Entry: Project approved by the District Approval Committee.
|
14-Oct-19 |
by Scott Carr |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
2-May-20 |
by Kim Muslusky |
Because of the COVID19 pandemic, this house build has to be delayed. We are unable to build the house at this time. We will complete the project when it is safe to do so.
|
2-May-20 |
by Kim Muslusky |
System Entry: Final Report signed by Kim Muslusky.
|
19-May-20 |
System Entry |
System Entry: Final Report signed by Susan Marsh.
|
19-May-20 |
by Elana Levens-Craig |
System Entry: Final report approved by the District Approval Committee.
|