17-Jul-13 |
System Entry |
Creation of project page.
|
17-Jul-13 |
System Entry |
Project sent for club signatures.
|
17-Jul-13 |
System Entry |
Project signed by Jim Stergeos.
|
18-Jul-13 |
System Entry |
Project signed by Vince Hrabal.
|
5-Aug-13 |
System Entry |
Project signed by Sharron Miles.
|
16-Sep-13 |
by Vince Hrabal |
We are in the process of obtaining student counts from the elementary schools. That process should be completed by 09-19-13, at which time dictionaries will be ordered. We anticipate the delivery of the dictionaries to be completed by the 3rd week of October.
|
28-Sep-13 |
System Entry |
Project approved by the District Approval Committee.
|
3-Dec-13 |
by Vince Hrabal |
Project has been completed as of 11-22-2013
|
21-Jan-14 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
3-Jun-14 |
System Entry |
Project has been implemented and final report uploaded.
|
3-Jun-14 |
System Entry |
Final report approved by the District Approval Committee.
|