Summary: Purchase and Install 4 benches along the path in Yesness Park, circling the pond.
The City of Casper was gifted the Harry Yesness Park in 1961 (originally part of the historic CY Ranch). It is a .60-mile loop surrounding a stocked, fishing pond. It is partially paved and located near 3 senior-housing communities as well as 2 Skilled Nursing Facilities. The Trail has an average grade of >5% there are 2 areas that are at 12%, the Trail is accessible however, there are no areas to rest along the path. In keeping with its mission to enrich the lives of seniors in the Casper area, Reveille Rotary wishes to continue with our Benches for Seniors program and install 4 benches along the Path. In addition to support from a District 5440 Grant, Reveille Rotary will finance the project. The total estimated project cost is $8,200 and the District is being asked for $3,100 of support. The cost of the benches has more than doubled over previous years, likely due to materials also doubling in price. The club members will assemble the benches, pour the concrete pads and install the benches working in conjunction with the City of Casper. The project is anticipated to be completed in 2022.
Paid
This project is "Paid". This means that the funds from the district have been issued. This project is now being ready for implementation. When this is done, a report needs to be uploaded on the project page and the "Reported" button needs to be clicked, then the status of the project will be changed to "Reported".
I cancelled the signature process because you need to change the Rotary year in the Description area to 22-23. Also you need next years Presidents signature in addition to yours.
3-May-22
by Randall J Looper
System Entry: Signature Process cancelled by user.
6-Jun-22
by Randall J Looper
Cynthia,
Your 22-23 club President needs to complete the District grant qualification questions and send the answers to me at elkruninn@yahoo.com. https://rotary5440.org/page/district-grant-qualifications
Randy
20-Jul-22
by Cyndi Brainard
System Entry: Project sent for club signatures.
20-Jul-22
by Cyndi Brainard
System Entry: Project signed by Cynthia.
1-Sep-22
by Randall J Looper
Cynthia,
Kammi has not signed the grant yet. I cannot approve it until she does. Can you send it to her again and email her that you are doing it so she will look for it.
Randy
1-Sep-22
by Kammi Shaw
System Entry: Project signed by Kammi Shaw.
15-Sep-22
by Randall J Looper
System Entry: Project approved by the District Approval Committee.
15-Sep-22
by Randall J Looper
System Entry: Check for DDF payment issued by Foundation Treasurer.
9-Jan-23
by Randall J Looper
Cynthia,
Please provide a quarterly history log update as to the status of this project.
12-Apr-23
by Randall J Looper
Cynthia,
Please provide a quarterly history log update as to the status of this project.
Randy
31-May-23
by Kammi Shaw
May 2nd we were able to prep the pad space for two of the benches. We are waiting for the city to install those two benches for us. We are waiting on the shipment of the other two benches so we can continue the process for those.