15-Aug-13 |
System Entry |
Creation of project page.
|
20-Aug-13 |
System Entry |
Project sent for club signatures.
|
20-Aug-13 |
System Entry |
Project signed by Kerri Redeker.
|
20-Aug-13 |
System Entry |
Project signed by Jeffrey Redeker.
|
13-Sep-13 |
System Entry |
Project approved by the District Approval Committee.
|
20-Sep-13 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
15-May-14 |
by Jeffrey Redeker |
Project Complete and all required data submitted to district 5-15-14
|
15-May-14 |
System Entry |
Project has been implemented and final report uploaded.
|
18-May-14 |
by Harry Charm |
Uploaded FINAL REPORT has been changed to PROGRESS REPORT & project status reverted to PAID.
|
18-May-14 |
System Entry |
Project reverted to 'Paid' status.
|
9-Jun-14 |
by Jeffrey Redeker |
Per your request the itemized invoice and cancelled check have been uploaded. We hope this closed this out. Thanks
|
9-Jun-14 |
System Entry |
Project has been implemented and final report uploaded.
|
24-Jun-14 |
System Entry |
Final report approved by the District Approval Committee.
|