30-Aug-13 |
System Entry |
Creation of project page.
|
2-Sep-13 |
System Entry |
Project sent for club signatures.
|
2-Sep-13 |
System Entry |
Project signed by Bill Stumbaugh.
|
2-Sep-13 |
System Entry |
Project signed by Ivan Alba.
|
4-Sep-13 |
System Entry |
Project signed by Hugo Murillo.
|
12-Sep-13 |
System Entry |
Project approved by the District Approval Committee.
|
18-Oct-13 |
by Ivan Alba |
Isabel and Lily Alba surveyed four classrooms at Tubman Charter School to determine which books should be purchased.
|
11-Nov-13 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
30-Jan-14 |
by Ivan Alba |
Books were purchased by Lidia Scinski (Tubman Principal) for each of four classrooms of students in grades 2 and 3.
|
8-Mar-14 |
System Entry |
Project has been implemented and final report uploaded.
|
3-Apr-14 |
by Marge Cole |
Club has been asked to complete a Final Report document and upload it to the grant website. It should include an itemization of the funds spent for this project.
|
6-May-14 |
System Entry |
Final report approved by the District Approval Committee.
|