P-4420

Rotary-Splash Pad

Description

Financing

Documents

Photos

History Logs

Project Description

Country: USA

Location: Diamondville, Wyoming

Total Budget: $12,500

Areas of Focus: Maternal and child health, Basic education and literacy, Community economic development

Activity Type: Community Development: Construction/Renovation

Summary: The Rotary Club of Kemmerer is spear heading a huge project to get a splash pad in our local community.


For years the people of our local communities have tried and tried to get a splash pad in our community but have lacked municipal support. We currently have an outdoor pool in our community, however, this pool is often broken, understaffed, and is in need of many costly repairs, which has caused the pool to be closed many summers. With a splash pad in our community people will be able to take their child outside to play and get exercise on those hot summer days. The timeline for this project will be fundraising this summer and fall with a installation date of June of 2023, with a grad opening of mid July, 2023. The design of the splash pad includes a recirculating water system, to reduce water use. Operational and maintenance cost will be minimal based on design. The Town of Diamondville has already committed to future operational and maintenance cost. Residents, visitors, and tourists are huge supporters of this project. We will be seeking funding from our local communities, community members, local companies big and small, and all the local clubs in our area to make this project possible. As of today we have established municipal support and are starting with a $40,000.00 commitment from the Town of Diamondville for a 1225 square foot splash pad! Rotary is going to be very involved in this project from fundraising the $140,000.00, dedication ceremony (serving food), instillation of educational and literacy activities around the splash pad.

Project Contact Person

District: 5440

Rotary Club of: Kemmerer

Primary Contact: Bridget Stewart

Email: bstewart@westernwyoming.edu

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2022-23 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Kemmerer (5440)

22-Jun-22

$10,000

$2,500

$12,500

Total

$10,000

$2,500

$12,500

Project Supporting Documents


[22-Dec-22]
Budget


[22-Nov-23]
FinalReport


[24-Oct-23]
Imageofcheckforsplashpad


[24-Oct-23]
SplashPadContract

Project Photos

History Log Entries

22-Jun-22

by Bridget Stewart

System Entry: Creation of project page.

28-Jun-22

by Bridget Stewart

System Entry: Project is now "Fully Pledged".

28-Jun-22

by Bridget Stewart

System Entry: Project sent for club signatures.

28-Jun-22

by Bridget Stewart

System Entry: Project signed by Bridget Stewart.

28-Jun-22

by Alexis Scherr

System Entry: Project signed by Alexis Scherr.

2-Aug-22

by Bridget Stewart

We are getting closer to having this project completed! We are over half way there!

19-Sep-22

by Bridget Stewart

We were not awarded this grant, because we submitted to late. We will apply in October if there is more funding.

2-Dec-22

by Bridget Stewart

System Entry: Signature Process cancelled by user.

2-Dec-22

by Bridget Stewart

System Entry: Project reverted to "Published".

2-Dec-22

by Bridget Stewart

System Entry: Project is now "Fully Pledged".

2-Dec-22

by Bridget Stewart

System Entry: Project sent for club signatures.

2-Dec-22

by Bridget Stewart

System Entry: Project signed by Bridget Stewart.

2-Dec-22

by Randall J Looper

System Entry: Signature Process cancelled by user.

21-Dec-22

by Randall J Looper

Bridgit,

You still need to upload a detailed budget of income and expenses to the documents area and complete the signature process with your and your club Presidents signature before I can approve the grant.

Randy

22-Dec-22

by Bridget Stewart

System Entry: Project sent for club signatures.

22-Dec-22

by Bridget Stewart

System Entry: Project signed by Bridget Stewart.

22-Dec-22

by Alexis Scherr

System Entry: Project reverted to "Submitted" - Alexis Scherr added to the list of signatories.

22-Dec-22

by Alexis Scherr

System Entry: Project signed by Alexis Scherr.

23-Dec-22

by Randall J Looper

System Entry: Project approved by the District Approval Committee.

23-Dec-22

by Randall J Looper

System Entry: Check for DDF payment issued by Foundation Treasurer.

12-Apr-23

by Randall J Looper

Bridgit,

Please provide a quarterly history log update as to the status of this project.

Randy

13-Apr-23

by Bridget Stewart

We should be breaking ground in May, hopefully! We have a ton of snow we are try to deal with to get to the location of the Splash Pad.

12-Jul-23

by Randall J Looper

Briget,

Please provide a quarterly history log update as to the status of this project.

Randy

13-Jul-23

by Bridget Stewart

We have great news! The cement is be poured today and we should have a splash pad up by hopefully this Labor Day!

14-Oct-23

by Randall J Looper

Bridget,

Was the project completed? If not p[lease provide an update.

23-Oct-23

by Bridget Stewart

We are hoping to finish the whole project today, October 23, 2023!

22-Nov-23

by Bridget Stewart

System Entry: Project has been implemented and final report uploaded.

22-Nov-23

by Randall J Looper

System Entry: Final report approved by the District Approval Committee.