Country: USA

Location: Morrill, Nebraska

Total Budget: $11,000

Area of Focus: Basic education and literacy

Activity Type: Community Development: Construction/Renovation

Summary: Public Library flooring upgrades


Morrill is a small farming community located in Western Nebraska. Our current Library was built by the WPA in 1936. In that same year the Morrill Rotary Club was chartered. We have always had a close relationship with the Library. We had our meetings there into the 1990's until building codes required us to close the kitchen. Our Library in an integral part of this community, providing not only books for young and old, but also audio and visual selections, computer and internet access, summer reading programs and much more. Past Rotary projects have replaced old windows with new, provided audio/visual equipment and provided labor for painting projects. Our latest project provided a small library kiosk in the park.

This project will replace flooring in the downstairs area of the Library. We will replace worn and torn carpet in the reading room and replace tile and stair treads (most likely containing asbestos) with new. This will be a hands on project as much as possible. We will remove the old flooring and stair tread and help the installers wherever possible. The project will proceed upon grant approval and funding. The club's funding is in place.

NOTE: The President, President-elect and the Grants Committee Chair (myself) have all watched and discussed the Grants Training video. I will provide pictures and estimate of work to be done in a later email

Project Contact Person

District: 5440

Rotary Club of: Morrill

Primary Contact: Steve Lutz

Email: slutz@prairieweb.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2023-24 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Morrill (5440)

26-Apr-23

$6,000

$5,000

$11,000

Total

$6,000

$5,000

$11,000

Project Supporting Documents

Project Photos

History Log Entries

26-Apr-23

System Entry

System Entry: Creation of project page.

15-May-23

by Steve Lutz

System Entry: Project sent for club signatures.

15-May-23

by Steve Lutz

System Entry: Project signed by Steve Lutz.

24-May-23

System Entry

System Entry: Project signed by Matthew Harris.

21-Jun-23

by Randall J Looper

Steve,

Please have your PE submit the answers to the district grant questions to myself or Robin. Once we receive those we will send a MOU for your PE to sign and send to us. This is the link to the questions

https://rotary5440.org/page/district-grant-qualifications

If you have any questions let me know.

Randy Looper

3-Jul-23

by Randall J Looper

System Entry: Project approved by the District Approval Committee.

9-Aug-23

by Randall J Looper

System Entry: Check for DDF payment issued by Foundation Treasurer.

14-Sep-23

by Steve Lutz

Received and deposited grant funds

14-Sep-23

by Steve Lutz

Received and deposited grant funds

1-Oct-23

by Steve Lutz

7 club members met at the library to tear out carpet in the downstairs children's reading room. We removed and disposed of the old carpet to prepare for Anderson Carpet to install the new carpet. This was done the next day on October 2,2023. The installation of the anteroom vinyl and the stair treads will be delayed until January, 2024.

No funds have been released at this time although we will do a partial release if requested by the flooring company.

10-Dec-23

by Steve Lutz

The first phase of the project (downstairs reading room carpet) has been completed and a check in the amount of $3133.50 has been issued for the completed work. The second phase is scheduled for January 8, 2024. A copy of the invoice has been added in the documents section.

7-Jan-24

by Steve Lutz

6 Rotarians met at the Library to remove the old carpet in the entryway in preparation for installation of new carpet and vinyl stair treads

19-Jan-24

by Steve Lutz

Installers finished the Library entry way PROJECT COMPLETE!!

26-Jan-24

by Randall J Looper

Steve,

Now that the project is compete please complete a district report found at the following link to our District website: https://www.rotary5440.org/page/district-amp-global-grants

At the bottom of the page under links please download the "District Report Form", Complete it, sign it and load it along with copies of the receipts for the project to the documents area of the grant, Once that is done please let me know and I can close out the grant.

Randy

31-Jan-24

by Randall J Looper

System Entry: Project has been implemented and final report uploaded.

31-Jan-24

by Randall J Looper

System Entry: Final report approved by the District Approval Committee.