Project Description

Country: USA

Location: Alma, Nebraska

Total Budget: $1,406

Area of Focus: Economic and community development

Activity Type: Community Development: General

Summary: Up dates in the City of Alma's park. The whole community will benefit.


Number one of a two part request: The community of Alma has a beautiful city park located on the west edge of Alma and recently due to storms and weather concerns several of the trees were destroyed. Our club wanted to be a part of replacing the trees and made plans to purchase 4 good sized trees to fill the void left in the damaged areas. The plan would be to have the trees planted by next fall depending on the recommendation for planting.

The second project was to purchase two four foot park benches for the city park and locate them near the new children's playground equipment located in the NE corner of the park. One of our members observed that there was not seating close to the equipment and being a grandpa himself felt it would be a great addition to the area.


Addendum to Project Description (added after the project was signed)

We are now waiting for the installation of the trees and benches in the spring of 2015. Project is set for completion with spring weather.

Project Contact Person

District: 5630

Rotary Club of: Alma

Primary Contact: Rick Calkins

Email: calkinslaw@gmail.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2014-15 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Alma (5630)

14-May-14

$406

$1,000

$1,406

Total

$406

$1,000

$1,406

Project Supporting Documents


[1-Aug-15]
Final report

 

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

14-May-14

System Entry

Creation of project page.

12-Jul-14

System Entry

Project sent for club signatures.

2-Sep-14

by Don Ehrke

The park benches are being ordered and the types of trees needed are being considered and will be planted this fall. Hopefully the benches will be here within 30 days.

3-Nov-14

by Don Ehrke

The Project is moving forward as the decision of what type of trees should be added in the park. We are working with the city officials to get this done. The tress may not be planted until this spring.

The park benches are to be ordered and hopefully in place within the next 30 days.

19-Nov-14

System Entry

Project signed by Scott McLaughlin.

16-Feb-15

System Entry

Signature Process cancelled by user.

16-Feb-15

System Entry

Project sent for club signatures.

16-Feb-15

System Entry

Project signed by Rick Calkins.

7-Apr-15

System Entry

Project approved by the District Approval Committee.

7-Apr-15

System Entry

Check for DDF payment issued by Foundation Treasurer.

1-Aug-15

System Entry

Project has been implemented and final report uploaded.

1-Aug-15

System Entry

Final report approved by the District Approval Committee.