G-1476

Maternity Ward Completion

Description

Financing

Documents

Photos

History Logs

Project Description

Region: Africa

Country: Uganda

Location: Kumi

Total Budget: $60,000

Areas of Focus: Disease prevention and treatment, Maternal and child health, Community economic development



We will be completing the new existing Maternity Building.

We will be installing new solar lighting, painting the interior of the building.

We will be providing new equipment for the Maternity Building, beds, chairs, solar refrigerators and misc medical equipment and supplies.

Once the building is complete we will be sending a medical team to host a medical clinic

Primary Host Partner

District: 5330

Rotary Club of: Rialto

Primary Contact: Barry David Valdez

Email: barryvaldez@msn.com

Primary International Partner

District: 9211

Rotary Club of: Kampala

Primary Contact: Barry David Valdez

Email: barryvaldez@msn.com

Project Status

Dropped
This project has been "Dropped". Check the history log entries to see why it was dropped.

Project listed for the 2017-18 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

There are no contributions yet for this project.

Remaining Amount to Raise

Additional Club Contribution (Needed) - Add a contribution

$40,000

-

$40,000

Amount Requested from The Rotary Foundation

$20,000

$0

$20,000

Total

$60,000

Note: as of July 1, 2015 there is a 5% additional support fee for cash contributions. This fee does not appear in the financials above because it does not apply if the funds are sent directly to the project account (without going through TRF, and therefore without Paul Harris credit). Clubs sending their cash contribution to TRF must be aware they will have to send an additional 5%.

Project Supporting Documents


There are no documents yet for this project.
Go to the administration page to upload documents.

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

13-Jan-18

System Entry

System Entry: Creation of project page.

2-Sep-18

System Entry

System Entry: Project dropped per lack of response to the carry-over notification emails.

© 2010 Philippe Lamoise - Website design by Philippe Lamoise, D2G Online