16-Aug-18 |
System Entry |
System Entry: Creation of project page.
|
15-Sep-18 |
by Jesse T. Campos |
System Entry: Pledge of $5,000 DDF by Deepak Gupta of District 3012.
|
20-Sep-18 |
by Mauro Carvalho Duarte Junior |
System Entry: Pledge of $1 by Mauro Duarte of the Rotary Club of Maringá-Colombo, District 4630.
|
20-Sep-18 |
by Mauro Carvalho Duarte Junior |
System Entry: Pledge of $5,000 DDF by Jesse Tanchanco of District 3780.
|
10-Oct-18 |
by Christopher J McLucas |
System Entry: Pledge of $516 by Christopher McLucas of the Rotary Club of Arlington (Sunrise), District 5790.
|
10-Oct-18 |
by Christopher J McLucas |
System Entry: Project is now "Fully Pledged".
|
11-Nov-18 |
by Fernando Riello |
System Entry: Pledge of $5,000 by Neelavathi of the Rotary Club of Karur Angels, District 3000.
|
18-Feb-19 |
by Fernando Riello |
Project submitted to TFR. Waiting for legal approval from D3000 India
|
1-Jul-19 |
by Fernando Riello |
All donations have been done by all enrolled partners. Rotary International have made deposit to Project account on June 26th. We will start implementing project from now on. Thank you to all for kind collaboration
|
2-Aug-19 |
by Fernando Riello |
System Entry: Application Sent to The Rotary Foundation through Member Access.
|
2-Aug-19 |
by Fernando Riello |
System Entry: Application approved by The Rotary Foundation.
|
2-Aug-19 |
by Fernando Riello |
System Entry: Payment has been issued by The Rotary Foundation.
|
16-Feb-20 |
by Fernando Riello |
Status on Feb 16th, 2020:
Recycling operation is already started on new building with much more room. We were able to get press machine from other partner, so we will replace one press machine from project by a Forklift that can help associates a lot, because today they need to drag big compacted recycled material by hand. Main road block to conclude this Project is to close building with wall to avoid rain ingress. Also the área were the recycling material is dropped needs a roof to prevent Rain and Strong sun. We will try to fund more Money to solve this problem. About additional USD10k will be required.
|
16-Sep-20 |
by Fernando Riello |
Project is in final stage. Next and final step is loading dock which is under preparation. Conclusion expected by end of October
|
5-Apr-21 |
by Fernando Riello |
System Entry: Final Report sent to The Rotary Foundation.
|
19-Jun-21 |
by Fernando Riello |
Project has been concluded and Final report has been inputted into Rotary Foundation web Page. Next step is to get report approval from Rotary
|
2-Sep-21 |
by Fernando Riello |
Project was already completed but Final Report still under evaluation by The Rotary Foundation
|
3-Jan-22 |
by Fernando Riello |
Received email from Rotary Foundation on Dez, 30th 2021 requesting additional information related to expense report. Such complementary information will be shared w/ TRF within Jan 2022. Expected Project Final report approval within 2022 Q1.
|
16-Mar-22 |
by Fernando Riello |
Additional documentation was requested by The Rotary Foundation in order to conclude expenses audit. By current pace, expectation to finnish audits should be May or Jun/2022.
|
2-Jun-22 |
by Fernando Riello |
System Entry: Final Report approved by The Rotary Foundation.
|