18-Dec-14 |
System Entry |
Creation of project page.
|
11-Jan-15 |
System Entry |
Project reverted to "Published".
|
11-Jan-15 |
System Entry |
Project is now "Fully Pledged".
|
11-Jan-15 |
System Entry |
Project is now "Fully Pledged".
|
13-Jan-15 |
by Marge Cole |
The District 5340 Rotary Foundation Committee has approved the match of $5000. in District Designated Funds (DDF) for this grant. It can proceed to application with The Rotary Foundation.
|
14-Apr-15 |
System Entry |
Application Sent to The Rotary Foundation through Member Access.
|
14-Apr-15 |
System Entry |
Application approved by The Rotary Foundation.
|
22-Jul-15 |
by Philippe Lamoise |
$15,000 contribution from Del Mar forwarded to TRF from the Matching Grants Website DAF.
|
6-Aug-15 |
by Philippe Lamoise |
Payment released by TRF. Funds should be in the account in 5-7 days.
|
16-Oct-15 |
System Entry |
Payment has been issued by The Rotary Foundation.
|
7-Mar-16 |
by Philippe Lamoise |
The CT Scan machine has been received after Government clearance and approval. The machine is being installed and we hope to inaugurate the project and have a dedication ceremony early April.
|
22-May-16 |
by Harish Singla |
The interim report has been saved on Global Grant Page of Rotary.org which needs authorisation from the respective Presidents
|
30-Jun-16 |
by Philippe Lamoise |
Progress report submitted to TRF in June 2016.
|
21-Oct-16 |
by Philippe Lamoise |
Interim report approved by TRF.
|
19-May-17 |
by Philippe Lamoise |
This project is still ongoing because there is a technical issue with the machine that was received in March 2016. The Rotary Club of Ludhiana is actively working to resolve this issue. For additional details, please contact the primary project partners.
|
5-Jun-17 |
by Philippe Lamoise |
Interim report submitted to TRF.
|
6-Oct-18 |
by Philippe Lamoise |
Following the audit report from TRF there was a committee meeting in District 3070 on 27-Sep-18 to discuss the resolution of this project. It was decided that a new proposal will be sent to TRF within 10 days.
|
26-Oct-18 |
by Philippe Lamoise |
A new CT Scan machine has been ordered from Siemens ad should be delivered within 12 to 15 weeks.
|
21-Jan-19 |
by Philippe Lamoise |
The new CT scan machine has been delivered.
|
29-May-19 |
by Philippe Lamoise |
The audit of this project has been closed successfully.
|
1-Oct-19 |
by Philippe Lamoise |
System Entry: Final Report sent to The Rotary Foundation.
|
1-Oct-19 |
by Philippe Lamoise |
System Entry: Final Report approved by The Rotary Foundation.
|