23-May-18 |
System Entry |
System Entry: Creation of project page.
|
25-May-18 |
by Rachel Ossyra |
Changed DDF to $750 to match Club's allocation for 2018-2019
|
2-Sep-18 |
by Rachel Ossyra |
This project is ongoing and waiting for the preparation of the District Grant application.
|
6-Sep-18 |
by Ryan Lawrence |
We sent a check back for the money we did not use last year. We are now waiting on approval for this grant. We are still interested in doing this project.
|
6-Sep-18 |
by Ryan Lawrence |
System Entry: Project sent for club signatures.
|
6-Sep-18 |
by Ryan Lawrence |
System Entry: Project signed by Ryan Lawrence.
|
6-Sep-18 |
by Toni Greathouse |
System Entry: Project signed by Toni Greathouse.
|
7-Sep-18 |
by Chuck Corrigan |
System Entry: Project signed by Charles Corrigan.
|
10-Sep-18 |
by Susan W Linn |
System Entry: Project signed by Susan W Linn.
|
2-Oct-18 |
by Ryan Lawrence |
Dictionaries have been ordered. We should be receiving them in the next week and delivering them to the 3rd graders on October 23.
|
16-Oct-18 |
by Rachel Ossyra |
System Entry: Project signed by Rachel Ossyra.
|
7-Nov-18 |
by Susan W Linn |
System Entry: Project signed by Susan W Linn.
|
8-Nov-18 |
System Entry |
System Entry: Project signed by JoAnne Ragona.
|
8-Nov-18 |
by Susan W Linn |
System Entry: Project approved by the District Approval Committee.
|
20-Nov-18 |
by Chuck Corrigan |
Payment of this grant is on hold until the Club submits its annual Rotary Foundation goals.
Chuck Corrigan
|
20-Nov-18 |
by Chuck Corrigan |
The Club's goals have been submitted, so payment will be released.
Chuck
|
29-Nov-18 |
by David Phelps - District Administrator |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
1-Apr-19 |
by Susan W Linn |
This is a reminder that the final report for your 2018-19 District Grant project is due upon completion of your club’s project. To complete your final report, log into your account on the District Grant Website.
|
8-May-19 |
by Susan W Linn |
This is a reminder to submit the final report for your club’s 2018 – 2019 District Grant. All final reports are due by JUNE 1, 2019.
Thanks
|
10-May-19 |
by Ryan Lawrence |
Uploaded our checks and narrative from our Dictionary Project. I also added a few photos from the delivery day.
|
20-May-19 |
by Ryan Lawrence |
Added Report and Payment Records in documents
|
20-May-19 |
by Rachel Ossyra |
System Entry: Project has been implemented and final report uploaded.
|
11-Jun-19 |
by Bill Lyman - Stewardship |
Stewardship review is complete. Meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. WL/LG
|
13-Jun-19 |
by Chuck Corrigan |
System Entry: Final report approved by the District Approval Committee.
|