1-Jun-18 |
by Dick Galitz |
System Entry: Creation of project page.
|
2-Sep-18 |
by Rachel Ossyra |
This project is ongoing and waiting for the preparation of the District Grant application.
|
2-Sep-18 |
by Dick Galitz |
Project remains in planning stage pending trip scheduling.
|
16-Oct-18 |
by Rachel Ossyra |
System Entry: Project sent for club signatures.
|
9-Nov-18 |
by Dick Galitz |
System Entry: Project signed by Dick Galitz.
|
10-Nov-18 |
by Rachel Ossyra |
System Entry: Project approved by the District Approval Committee.
|
1-Dec-18 |
by David Phelps - District Administrator |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
27-May-19 |
by Susan W Linn |
This is a reminder that the final reports for your 2018-19 District Grant project are due this Saturday, June 1, 2019. To complete your final report, log into your account on the District Grant Website.
|
16-Jun-19 |
by Susan W Linn |
This is a reminder that the final report for your club’s 2018-19 District Grant project is past due. It is very important that you complete the final report as quickly as possible, and no later than June 30th.
The District Grants Committee cannot close the 2018-19 grant with Rotary International until your final report is complete.
Please log into your account on the District Grant Website to complete the report.
Thanks
|
27-Jun-19 |
by Susan W Linn |
The final report for your club’s 2018- 19 District Grant project is past due. The District Grants Committee cannot close the current grant from Rotary International until your club’s final report is submitted. This means that no club can receive their funds for 2019 – 2020 until your report is completed.
Please submit your final report by Sunday June 30th. To complete your report, log into your account on the District Grant Website.
|
27-Jun-19 |
by Susan W Linn |
The final report for your club’s 2018- 19 District Grant project is past due. The District Grants Committee cannot close the current grant from Rotary International until your club’s final report is submitted. This means that no club can receive their funds for 2019 – 2020 until your report is completed.
Please submit your final report by Sunday June 30th. To complete your report, log into your account on the District Grant Website.
|
29-Jun-19 |
by Dick Galitz |
Entered Roger Iliff's Honduras Trip Expenses plus Chuck Newman's Honduras Land Expenses.
|
30-Jun-19 |
by Dick Galitz |
Uploaded Chuck Newman's air travel expenses. Air and land travel expenses for Chuck and Roger totaled $4,180.99. Investigative trip very successful leading to four Global Grants for four Simple School projects.
|
30-Jun-19 |
by Dick Galitz |
System Entry: Project has been implemented and final report uploaded.
|
31-Aug-19 |
by Bill Lyman - Stewardship |
After full review of all paperwork, Stewardship review complete. Meets all necessary criteria. Final report reviewed. Project okay to be approved by District Approval Committee. WL & LG
|
31-Aug-19 |
by Rachel Ossyra |
System Entry: Final report approved by the District Approval Committee.
|