Country: USA

Location: Meridian Idaho

Total Budget: $4,985

Area of Focus: Community economic development

Activity Type: Community Development: Construction/Renovation

Summary: Provide ADA-accessible drinking fountain at trail head of new pedestrian park in Meridian


This project is to install a drinking fountain at the trail head of a new pedestrian park in Meridian that will be accessible to anyone on foot, on a bike, or using a wheelchair. The drinking fountain will have three access points to serve all abilities and designed to meet ADA requirements. The park and trail system is located in a currently under-served part of the community. Rotarians are involved in the following ways: 1. In the planning phase with Mike Barton and the City Parks planning committee (time in meetings); 2. in choosing and purchasing the drinking fountain (quote attached) 3. Directly installing the foundation with the parks dpt supervision; 4. installing the recognition plaque in the concrete near the drinking fountain with the parks dpt supervision; and 5. planning and delivering an open house at the pedestrian park trail head. We will provide Rotary club and Rotary Foundation recognition on the fountain.

Project Contact Person

District: 5400

Rotary Club of: Meridian

Primary Contact: Janice Fulkerson

Email: jfunifyconsulting@outlook.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2020-21 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Meridian (5400)

12-Mar-20

$2,493

$2,492

$4,985

Total

$2,493

$2,492

$4,985

Project Supporting Documents

Project Photos

History Log Entries

12-Mar-20

System Entry

System Entry: Creation of project page.

14-Mar-20

by Janice Fulkerson

System Entry: Project reverted to "Published".

14-Mar-20

by Janice Fulkerson

System Entry: Project is now "Fully Pledged".

14-Mar-20

by Janice Fulkerson

System Entry: Project sent for club signatures.

14-Mar-20

by Marianne Barker

System Entry: Signature Process cancelled by user.

16-Mar-20

by Ken Courville

System Entry: Project sent for club signatures.

16-Mar-20

by Ken Courville

System Entry: Project signed by Ken Courville.

16-Mar-20

by Marianne Barker

System Entry: Signature Process cancelled by user.

1-May-20

by Janice Fulkerson

System Entry: Project reverted to "Published".

1-May-20

by Janice Fulkerson

System Entry: Project is now "Fully Pledged".

14-May-20

by Marianne Barker

System Entry: Project reverted to "Published".

14-May-20

by Marianne Barker

System Entry: Project is now "Fully Pledged".

14-May-20

by Marianne Barker

System Entry: Project reverted to "Published".

14-May-20

by Marianne Barker

System Entry: Project is now "Fully Pledged".

15-May-20

by Janice Fulkerson

System Entry: Project sent for club signatures.

15-May-20

by Janice Fulkerson

System Entry: Project signed by Janice Fulkerson.

19-May-20

System Entry

System Entry: Project signed by Ken Courville.

15-Jul-20

by Ines Crespo

System Entry: Project approved by the District Approval Committee.

14-Aug-20

by T. J. Adams

System Entry: Check for DDF payment issued by Foundation Treasurer.

1-Jan-21

by Janice Fulkerson

Drinking fountain was purchased; the Rotary recognition plaque was designed and completed. Both items were delivered to the City of Meridian Parks & Recreation for storage. Installation and water hook-up will occur when weather warms up to appropriate temperatures.

17-Apr-21

by Marianne Barker

Deadline for final (or progress) report is May 15, 2021. If fountain is not yet installed, please enter a history log with an estimated date for project completion. Late report or no report may result in the club losing eligibility for a grant in 2021-22.

17-Apr-21

by Janice Fulkerson

Drinking Fountain and Rotary Plaque installation planned for May 8th. COVID and spring weather delays are over.

11-May-21

by Janice Fulkerson

Final Grant Report uploaded. 5-11-2021

11-May-21

by Ines Crespo

Are you ready to finalize this grant? If you have your final report and supporting documents uploaded, navigate to the Administration side of the Description tab. Once there, click the Reported button. If you have any questions, reach out to Ines Crespo, District Grants Subcommittee Chair, at (208) 320-8494 or ines@glassinbalance.com.

12-May-21

by Janice Fulkerson

System Entry: Project has been implemented and final report uploaded.

17-May-21

by Bob Rose

I have audited this project and I approve it.

17-May-21

by Bob Rose

System Entry: Final report approved by the District Approval Committee.