21-Jul-20 |
by Ines Crespo |
District Grant applications were due June 1. The District Block Grant has already been submitted and approved by the Rotary Foundation. At this time, all district grant funds have been claimed. If a club needs to return funds, we may consider your request at that time. Ines Crespo, District Grants Chair, ines@glassinbalance.com
|
21-Jul-20 |
System Entry |
System Entry: Creation of project page.
|
2-Nov-20 |
by Cody Eckman |
System Entry: Project sent for club signatures.
|
2-Nov-20 |
by Cody Eckman |
System Entry: Project signed by Cody Eckman.
|
16-Feb-21 |
by Cody Eckman |
This was not funded
|
15-Apr-21 |
by Marianne Barker |
After telecon with Cody, I changed cancelled the signatures and changed the grant year to 2021-22.
|
15-Apr-21 |
by Marianne Barker |
System Entry: Signature Process cancelled by user.
|
25-May-21 |
by Phillip Quayle |
System Entry: Project sent for club signatures.
|
25-May-21 |
by Phillip Quayle |
System Entry: Project signed by Shelby Millar.
|
26-May-21 |
by Phillip Quayle |
System Entry: Project signed by Phillip Quayle.
|
2-Aug-21 |
by Ines Crespo |
System Entry: Project approved by the District Approval Committee.
|
24-Aug-21 |
by Marianne Barker |
System Entry: Check for DDF payment issued by Foundation Treasurer.
|
1-Mar-22 |
by Ines Crespo |
Has this project been completed? This is a reminder that your progress or final report is due by May 14, 2022. Thank you!
|
15-Apr-22 |
by Ines Crespo |
Reminder: A progress or final report is due by May 15, 2022. Please reach out to District Grants Chair, Ines Crespo, at ines@glassinbalance.com or 208-320-8494 with any questions. Thank you!
|
26-Apr-22 |
by Cody Eckman |
System Entry: Project has been implemented and final report uploaded.
|
14-May-22 |
by Bob Rose |
I audited this project. I will approve it when you provide confirmation of the $420.00 expenditure. This can be: an invoice that shows paid, a credit card payment, or check information - date, paid to and check number.
|
16-May-22 |
by Bob Rose |
I have audited this project and I approve it.
|
17-May-22 |
by Ines Crespo |
System Entry: Final report approved by the District Approval Committee.
|