The Maternity Darcy Vargas is the principal Maternity at North of Santa Catarina State, in Brazil's South Region. It attends 28.700 mothers a year. There is a bank of human milk for breastfeeding babies in bad situation. We need to improve that, collecting milk from mothers who just had their babies, colaborating with the Intensive Care Unit (UTI)and others babies who for various reasons can not be breastfed by their real mothers. We need an utility vehicle fitted with termal box for the collection of human milk. Also extractors milk bombs and other components.
Dropped
This project has been "Dropped". Check the history log entries to see why it was dropped.
Project listed for the 2017-18 Rotary Year.
Proposed Financing
Existing Contributions Towards This Project
Date
Cash
DDF
Total
Joinville-Cidade das Flores (4650)
11-May-16
$1,000
$10,000
$11,000
Amount Requested from The Rotary Foundation
$500
$10,000
$10,500
Total
$21,500
Note: as of July 1, 2015 there is a 5% additional support fee for cash contributions. This fee does not appear in the financials above because it does not apply if the funds are sent directly to the project account (without going through TRF, and therefore without Paul Harris credit). Clubs sending their cash contribution to TRF must be aware they will have to send an additional 5%.
Project Supporting Documents
There are no documents yet for this project. Go to the administration page to upload documents.
Project Photos
There are no photos yet for this project.
Go to the administration page to upload photos.
History Log Entries
11-May-16
System Entry
Creation of project page.
18-Oct-17
by Mark Kirkpatrick
Please note, I included full pledge however we are awaiting DDF approval from D5340 for remaining funds.
18-Oct-17
System Entry
System Entry: Pledge of $3,286 with $3,286 DDF by Mark Kirkpatrick of the Rotary Club of San Diego Coastal, District 5340.
18-Oct-17
System Entry
System Entry: Project is now "Fully Pledged".
19-Oct-17
by Janice Kurth
D5340 is out of DDF for this Rotary year and cannot approve any additional DDF until we begin approving grants for 2018-2019, which will likely be in the March-April 2018 time frame.
16-Feb-18
by Mark Kirkpatrick
Received email request for update. Awaiting D5340 Global Grant process in April to determine if DDF will be allocated to this project. Thx
13-Mar-18
by Mark Kirkpatrick
Project will be cancelled. San Diego Coastal Rotary Club will withdrawal committed funds & DDF request.
26-Mar-18
by Mirian Ried Puerta
This project need to be canceled. We Got the resources here in Brazil.
2-Sep-18
System Entry
System Entry: Fully Pledged project dropped per lack of response to the carry-over notification emails.