P-2013

Earthquake Relief - Rebuild

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Mexico

Location: Cuoyuca de Andrade

Total Budget: $6,000

Area of Focus: Economic and community development

Activity Type: Community Development: Disaster Recovery

Summary: Rebuild 1 home in the mountain town of Cuoyuca de Andrade damaged by the September 2017 earthquake.


The club is partnering with the Rotary Club of Puebla Mirador in Puebla, Mexico to rebuild 1 home in the mountain town in Cuoyaca de Andrade, near the epicenter of the Mexican Earthquake in September of 2017. The Club has a trusted person who will supervise the project on a daily basis and club members will go to oversee it periodically.

# of Rotarians participating: 20+

# of non-Rotarians benefitting: One family

Expected Completion Date: May 30, 2018

Project Contact Person

District: 6450

Rotary Club of: Chicago Little Village

Primary Contact: Pam Brockman

Email: pam.brockman@att.net

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2017-18 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Naperville (6450)

18-Feb-18

$3,583

$2,417

$6,000

Total

$3,583

$2,417

$6,000

Project Supporting Documents

Project Photos

History Log Entries

18-Feb-18

by Rachel Ossyra

System Entry: Creation of project page.

18-Feb-18

by Rachel Ossyra

System Entry: Project sent for club signatures.

18-Feb-18

by Rachel Ossyra

System Entry: Project signed by Rachel Ossyra.

18-Feb-18

by Rachel Ossyra

System Entry: Project approved by the District Approval Committee.

19-Feb-18

by David Phelps

System Entry: Check for DDF payment issued by Foundation Treasurer.

25-May-18

by Rachel Ossyra

Final Report Reminder sent

2-Jul-18

by Pam Brockman

System Entry: Project has been implemented and final report uploaded.

27-Jul-18

by Bill L

In order for Stewardship to approve, proof of purchase for a total of $4,834 USD must be shown, either by copies of the cancelled check(s) or copies of a bank statement showing a total transfer of US funds.

Bill and Lesley

4-Aug-18

by Rachel Ossyra

Bank transfer receipt uploaded to Photos tab by Pam Brockman

4-Aug-18

by Rachel Ossyra

System Entry: Final report approved by the District Approval Committee.