29-Aug-11 |
System Entry |
Creation of project page.
|
29-Aug-11 |
System Entry |
Project sent for club signatures.
|
29-Aug-11 |
System Entry |
Project signed by Marge Cole.
|
29-Aug-11 |
System Entry |
Signature Process cancelled by user.
|
29-Aug-11 |
System Entry |
Project sent for club signatures.
|
29-Aug-11 |
System Entry |
Project signed by Marge Cole.
|
1-Sep-11 |
System Entry |
Signature Process cancelled by user.
|
1-Sep-11 |
System Entry |
Project sent for club signatures.
|
1-Sep-11 |
System Entry |
Project signed by Marge Cole.
|
2-Sep-11 |
System Entry |
Project signed by Lydia Stewart.
|
15-Sep-11 |
System Entry |
Project approved by the District Approval Committee.
|
17-Oct-11 |
by Judy Gallegos |
Check 1064 delivered to district office for signatures
|
17-Oct-11 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
14-Apr-12 |
System Entry |
Project has been implemented and final report uploaded.
|
14-Apr-12 |
System Entry |
Final report approved by the District Approval Committee.
|