Country: USA

Location: Twin Falls

Total Budget: $2,800

Areas of Focus: Maternal and child health, Economic and community development

Activity Type: Community Development: Volunteer Services

Summary: New Outdoor Playhouse and mulch for entire play area for at risk children.


Currently the Crisis Center of the Magic Valley has a very old playhouse that the kids love, but it is unsafe and falling apart and they have no funds to replace it. Estimated cost for a new wooden set is $2,000, they also need new mulch in the play area at this point what they have is very old and it is not safe for the kids as they are always hurting their feet on it. The cost to replace entire area with rubber mulch is $800. The club will assemble the playhouse as well as install the rubber mulch. Timeline will be dependent on equipment arrival. Once equipment has arrived we will tear down the old playhouse and dispose of it, lay the new mulch, and then assemble the new playhouse within a month. This project will greatly impact woman and children that are at risk of domestic violence, sexual assault and other abuse issues in 8 counties of south central Idaho. Each year the crisis center shelters thousands of woman and their children. Seventy five percent of the women who come bring their children. The crisis center reaches thousands of people each year with it's services. Without community assistance they are unable to shelter these abused woman and children. Our goal in this project is to help the crisis center have a fun, safe and healing environment for children that have experienced trauma due to domestic violence, physical/mental abuse, sexual abuse and so many other inconceivable, unspeakable life events.

Project Contact Person

District: 5400

Rotary Club of: Twin Falls-After Hours

Primary Contact: Jennifer

Email: czjcook4426@gmail.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2014-15 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

District 5400 DDF

29-Aug-14

-

$2,035

$2,035

Twin Falls-After Hours (5400)

12-Dec-14

$765

-

$765

Total

$765

$2,035

$2,800

Project Supporting Documents


[4-May-15]
DDF Check Image


[17-Aug-15]
Final Report


[17-Aug-15]
Idaho Concrete Donation


[17-Aug-15]
Lowes Receipts


[18-May-15]
Mulch Receipt


[6-May-15]
playhouse receipt

 

Project Photos

History Log Entries

29-Aug-14

System Entry

Creation of project page.

4-Sep-14

System Entry

Project sent for club signatures.

4-Sep-14

System Entry

Project signed by Sand March.

4-Sep-14

System Entry

Project signed by Jennifer.

8-Sep-14

System Entry

Project signed by Cari Kaster.

15-Oct-14

System Entry

Signature Process cancelled by user.

15-Oct-14

System Entry

Project reverted to "Published".

23-Oct-14

by Cari Kaster

Project has been approved for $2,035 in DDF. Please revise the financing tab showing where the additional $765 will be coming from for completion of this project. Please re-sign the grant application certifying the change. Once these items are complete the district will issue a check to your club. If you need further information please contact me at coaster@filertel.com.

12-Dec-14

System Entry

Pledge of $765 by Jennifer of the Rotary Club of Twin Falls-After Hours, District 5400.

12-Dec-14

System Entry

Project is now "Fully Pledged".

12-Dec-14

System Entry

Project sent for club signatures.

12-Dec-14

System Entry

Project signed by Jennifer.

15-Dec-14

System Entry

Project approved by the District Approval Committee.

23-Dec-14

System Entry

Check for DDF payment issued by Foundation Treasurer.

9-Mar-15

by Jennifer

Held our annual fundraiser and was able to earn the funds to support our grant and complete the project. Contacted the Crisis Center with the good news and they are getting us the information to order the items.

28-Apr-15

by Jennifer

Club met and made the final decision on which playhouse to order. We went online and ordered the playhouse. We also discussed increasing the cement pad to accommodate the size of the new playhouse being larger then the old playhouse.

4-May-15

by Jennifer

Notice received that playhouse has been shipped

5-May-15

by Jennifer

Travis from Idaho Concrete company went out to increase the size of our cement pad and decided that the existing pad would need to be completely removed. Idaho Concrete agreed to remove the old pad and lay a pad large enough to accommodate the new playhouse.

5-May-15

by Jedd Thomas

An e-mail reminder sent to Jennifer for this project's final or progress report to be added to "Project Supporting Documents" by the May 15 due date. Supporting documents are also needed.

7-May-15

by Jennifer

Club members met at the crisis center and removed the old playhouse.

18-May-15

by Jennifer

Ordered and paid for new mulch for playground. Receipt for $622.40 uploaded

19-May-15

by Jennifer

The club got together and removed the old mulch and put in new. We also put together the playhouse we are scheduled to go back on the 3rd of June to put the finishing touches on the playhouse

9-Jul-15

by Marianne Barker

Is this project now complete? Please submit a final report using the form located in the grants folder at www.rotary5400.org and upload it to this site. Please upload any additional receipts for materials.

29-Jul-15

by Jennifer

Put the finishing touches on the new playhouse. It is done and ready to go

10-Aug-15

by Marianne Barker

Please submit a final report, typed on the report form available in the grants folder at www.rotary5400.org. Include in-kind contributions (such as Idaho Concrete) as both a revenue source and an expense. Upload the completed report to P-752 on matchinggrants.org along with any additional receipts for expenditures. Questions? Call Cari Kaster at 539-1519 or Marianne Barker at 308-5617.

17-Aug-15

by Jennifer

final receipts and report has been uploaded

22-Aug-15

System Entry

Project has been implemented and final report uploaded.

24-Aug-15

by Jedd Thomas

The reports and supporting information have been audited as of this date, and documentation is sufficient to allow for this grant file to be closed.

27-Aug-15

System Entry

Final report approved by the District Approval Committee.