G-149

Nkondo Expanded Irrigation

Description

Financing

Documents

Photos

History Logs

Project Description

Region: Africa

Country: Uganda

Location: Nkondo, Budiope County

Total Budget: $42,400

Areas of Focus: Water, sanitation and hygiene, Community economic development



View Online
Proposal Form

This is follow up project to GG25002, Nkondo Adopt a Village, which included a water component that also covers micro-irrigation. The Nkondo community is basically a rural agriculture community, and the objective of the new project is to expand the scope of irrigation during the dry season, thus maximising returns from high yield crops by marketing outside peak seasons: the challenge of most agricultural communities in Uganda is that they all plant at the same time during the rains; harvest at the same time, and sell when prices are at their lowest. This project will help in the establishment of several small scale valley dams (to be excavated by the community) set up with suitable plastic sheeting underlayers to ensure water retention. A related component will dwell on product storage so that selling during peak production seasons is avoided.

See photos of an existing "valley dam" on the "Photos" tab.

Primary Host Partner

District: 9211

Rotary Club of: Kampala-North

Primary Contact: Francis Tusubira

Email: fftusu@gmail.com

Primary International Partner

District: 5340

Rotary Club of: Del Mar

Primary Contact: Philippe Lamoise

Email: philippe@lamoise.net

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by The Rotary Foundation. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2011-12 Rotary Year.

The TRF Grant application number is #25920.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

San Diego Coastal (5340)

22-Jun-11

$2,000

$2,000

$4,000

La Jolla Golden Triangle (5340)

7-Dec-11

$2,500

$2,500

$5,000

Kampala-North (9211)

10-Dec-11

$2,500

$6,200

$8,700

Escondido East (5340)

16-Feb-12

$2,000

$2,000

$4,000

Oceanside (5340)

28-Feb-12

$1,000

$1,000

$2,000

Amount Requested from The Rotary Foundation

$5,000

$13,700

$18,700

Total

$42,400

Project Supporting Documents

Project Photos

History Log Entries

22-Jun-11

System Entry

Creation of project page.

4-Jul-11

System Entry

Project is now "Fully Pledged".

11-Jul-11

by Philippe Lamoise

Contribution of $10,000 DDF approved by the District 5340 Rotary Foundation Committee.

6-Dec-11

System Entry

Project reverted to "Published".

7-Dec-11

System Entry

Pledge of $2,500 by Pamela Russell of the Rotary Club of La Jolla Golden Triangle, District 5340.

10-Dec-11

System Entry

Pledge of $2,000 with $5,000 DDF by Tusu Tusubira of the Rotary Club of Kampala-North, District 9200.

10-Dec-11

System Entry

Project is now "Fully Pledged".

10-Dec-11

System Entry

Project reverted to "Published".

10-Dec-11

System Entry

Pledge of $2,500 with $6,200 DDF by Tusu Tusubira of the Rotary Club of Kampala-North, District 9200.

7-Jan-12

System Entry

Project is now "Fully Pledged".

9-Jan-12

by Pam Russell

DDF of $7,500 approved today by District Rotary Foundation Committee

31-Jan-12

by Mark Kirkpatrick

Updated Grant base don Board response from SD Coastal. Will find clubs with matching funds. Deadline for finding funds: March 9th.

31-Jan-12

System Entry

Project reverted to "Published".

16-Feb-12

by Mark Kirkpatrick

Escondido East pledged $2,000. Made Changes to DDF for balance.

16-Feb-12

System Entry

Pledge of $2,000 with $2,000 DDF by Holly Merkel of the Rotary Club of Escondido East, District 5340.

28-Feb-12

System Entry

Pledge of $1,000 with $1,000 DDF by Mike Curtin of the Rotary Club of Oceanside, District 5340.

3-Mar-12

by Mark Kirkpatrick

Project has been fully funded.

3-Mar-12

System Entry

Project is now "Fully Pledged".

3-Mar-12

System Entry

Proposal Sent to The Rotary Foundation through Member Access.

12-Mar-12

System Entry

Proposal approved by The Rotary Foundation.

9-Apr-12

by Pam Russell

The District 5340 Rotary Foundation committee approved the reallocation of DDF as indicated in the current financing today for a total of $7,500.

23-May-12

by Philippe Lamoise

Application completed in Member Access and ready to be signed by primary contacts and district leadership.

24-May-12

System Entry

Application Sent to The Rotary Foundation through Member Access.

31-May-12

by Philippe Lamoise

TRF came back to us with 2 questions on the application about monitoring and evaluation of the project, and about capacity building for crop processing.

21-Jun-12

System Entry

Application approved by The Rotary Foundation.

2-Oct-12

by Frank Sebbowa

Project 149 is almost fully paid up.

Completion time is still end Dec 2012

24-Jan-13

by Philippe Lamoise

Bank information has been uploaded and the project has been authorized by both club presidents, so it should be forwarded for payment shortly.

7-Feb-13

System Entry

Payment has been issued by The Rotary Foundation.

12-Nov-13

by Philippe Lamoise

Contractor identified; Local government discussed and approved the project and agreed to take up ownership once done; Land owners where the dams are to be located have all formally written granting land. Challenge is that it is the middle of heavy rains, and that is not suitable for excavation. We holding on for the rains to tail off.

7-Apr-14

by Marge Cole

A Progress Report for this grant was due on February 7, 2014--it is two months overdue. It is imperative to report progress to The Rotary Foundation at required intervals to protect Club and District ability to participate in additional grants.

18-Jun-14

by Francis Tusubira

Three dams completed, 4th in progress

18-Jun-14

by Philippe Lamoise

The late progress report was finally officially submitted today on the RI website, with the last authorizing signature from the President of the Del Mar Rotary Club.

3-Feb-15

by Philippe Lamoise

Per Tusu: Four of the valley dams were completed, and the current Governor visited them. He was impressed by the scope and possibilities. The 5th was half done before the extended rains we have had for almost 7 months came in. We are now in a dry season, and the last dam should be completed soon.

30-Jun-16

by Philippe Lamoise

Last interim report submitted in Feb 2016. Final report coming soon.

18-Oct-16

by Philippe Lamoise

We are in the process of getting the authorization from TRF to spend the remaining funds on project-related activities. The project will be closed after these funds are spent.

28-Mar-17

by Francis Tusubira

System Entry: Final Report sent to The Rotary Foundation.

20-Apr-17

by Philippe Lamoise

Last signature collected on the Final Report.

3-May-17

by Philippe Lamoise

System Entry: Final Report approved by The Rotary Foundation.