P-1107

Rebuilding school

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Nepal

Location: Deuralitar Village

Total Budget: $8,000

Area of Focus: Basic education and literacy

Activity Type: Education: General

Summary: Rebuilding of school in Nepal


This school was damaged by an earthquake and this project is to rebuild several of the classroooms. See the document Application/Budget for a more detailed description.

Project Contact Person

District: 5440

Rotary Club of: Fort Collins After Work

Primary Contact: Jim Epstein

Email: james.epstein@gmail.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2015-16 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Fort Collins After Work (5440)

27-Nov-15

$4,000

$4,000

$8,000

Total

$4,000

$4,000

$8,000

Project Supporting Documents


[27-Nov-15]
Application/Budget


[1-May-16]
Final Report

 

Project Photos


There are no photos yet for this project.
Go to the administration page to upload photos.

History Log Entries

27-Nov-15

System Entry

Creation of project page.

27-Nov-15

System Entry

Project sent for club signatures.

27-Nov-15

System Entry

Project signed by Jim Epstein.

27-Nov-15

System Entry

Signature Process cancelled by user.

27-Nov-15

System Entry

Project sent for club signatures.

27-Nov-15

System Entry

Project signed by Jim Epstein.

8-Dec-15

System Entry

Project reverted to "Submitted" - Ron Hogan added to the list of signatories.

8-Dec-15

System Entry

Project signed by Ron Hogan.

18-Dec-15

System Entry

Project approved by the District Approval Committee.

18-Dec-15

System Entry

Check for DDF payment issued by Foundation Treasurer.

4-Apr-16

by Jim Epstein

Report due 8/5/16

1-May-16

System Entry

Project has been implemented and final report uploaded.

1-May-16

System Entry

Final report approved by the District Approval Committee.