P-1802

Helena Garden Park

Description

Financing

Documents

Photos

History Logs

Project Description

Country: Montana

Location: Helena

Total Budget: $11,880

Area of Focus: Economic and community development

Activity Type: Community Development: General

Summary: 6th Ward Garden Park Trellis Lattice Panels and Benches


The Project provides trellises, benches, landscaping, and signage within Helena's 6th Ward Garden Park. The City project is part of a larger renewal to a once blighted neighborhood. Whth design elements laid out, initial plantings made, walkways built, and playground equipment installed, there is a need for shaded resting places.

Project Contact Person

District: 5390

Rotary Club of: Helena Sunrise

Primary Contact: Murray Strong

Email: murstrong1958@gmail.com

Project Status

Completed
This project is "Completed". This means the project has been implemented and the report was accepted by the district leadership. The project will stay listed on this website as a testimony of the achievements of the project partners.

Project listed for the 2017-18 Rotary Year.

Proposed Financing

Existing Contributions Towards This Project

Date

Cash

DDF

Total

Helena Sunrise (5390)

18-Jul-17

$7,500

$4,380

$11,880

Total

$7,500

$4,380

$11,880

Project Supporting Documents

Project Photos

History Log Entries

18-Jul-17

by Brian Furey

System Entry: Creation of project page.

16-Dec-17

by Murray Strong

System Entry: Project is now "Fully Pledged".

27-Dec-17

by Suzanne M Carstens

System Entry: Project sent for club signatures.

27-Dec-17

System Entry

System Entry: Project signed by Dan McLean.

28-Dec-17

System Entry

System Entry: Project signed by Murray Strong.

31-Dec-17

by Suzanne M Carstens

System Entry: Project approved by the District Approval Committee.

31-Dec-17

by Suzanne M Carstens

System Entry: Check for DDF payment issued by Foundation Treasurer.

2-Jul-18

by Murray Strong

System Entry: Final Report signed by Murray Strong.

2-Jul-18

System Entry

System Entry: Final Report signed by Dan McLean.

3-Jul-18

by Gordon Finney

System Entry: Final report approved by the District Approval Committee.

14-Jul-18

by Philippe Lamoise

System Entry: Project reverted to 'Paid' status.

31-Jul-18

by Murray Strong

System Entry: Final Report signed by Murray Strong.

2-Aug-18

System Entry

System Entry: Final Report signed by Dan McLean.

17-Sep-18

by Cheryl Rickmond

System Entry: Final report approved by the District Approval Committee.