28-Apr-11 |
System Entry |
Creation of project page.
|
1-Sep-11 |
System Entry |
Project sent for club signatures.
|
1-Sep-11 |
System Entry |
Project signed by Julie Lien.
|
18-Sep-11 |
System Entry |
Project signed by Kirk Collins.
|
20-Sep-11 |
by Mandyam Venkatesh |
The project is approved by the District and expect funding the project soon
|
21-Sep-11 |
System Entry |
Project approved by the District Approval Committee.
|
17-Oct-11 |
by Judy Gallegos |
Check 1042 delivered to district office for signatures
|
17-Oct-11 |
System Entry |
Check for DDF payment issued by Foundation Treasurer.
|
16-Feb-12 |
by Mandyam Venkatesh |
Seven Rotarians including myself from our club visited the project on 10 Feb 2012 and satisfied with the progress. The project is on schedule and is 50% complete.
|
7-May-12 |
by Radia Bencheikh |
Project completed in April 2012. Final report along with bank statements, invoices and photos uploaded.
|
5-Jun-12 |
System Entry |
Project has been implemented and final report uploaded.
|
5-Jun-12 |
System Entry |
Final report approved by the District Approval Committee.
|